Item 5H. Receive Mississippi Gateway Regional Park Final Budget Update
Superintendent's Recommendation:
NO ACTION REQUIRED; THIS ITEM IS FOR INFORMATION AND DISCUSSION.
Prepared By: Jason Zemke, Senior Manager of Architecture and Matt Swenson, Project Manager.
Background:
The Park District had a goal to roll out a newly redeveloped destination park in 2026, to serve as a gateway for everyone to connect with the Mississippi River and its dynamic environment. Exceeding expectations, it has already been 14 months since the Grand Opening of this now nationally recognized and award-winning park, and visitation has increased more than 500% since before breaking ground in 2023. Staff are proud to report that not only was this project delivered ahead of schedule, but also under budget.
Staff last reported, in August 2025, a surplus of $79,058 in unassigned funds and a remaining construction contingency of $530,462. At that time, there were still 32 pending change orders that had either not yet been fully executed or were still being negotiated. Some of these change orders resulted in a credit to the project, while a majority resulted in additional expenses. Also, as can be the case with many projects of this magnitude, the first year of staff and public interaction with the new features tends to reveal issues that require additional attention and/or correction. One example of this was the Mini-Mississippi, where staff recognized that the combination of stamped concrete and the specified sealer resulted in a surface texture that was more slippery than desired, and so contingency funding was used to correct this potential safety concern. Also, the Board may recall that the Mini-Mississippi was granted a temporary permit to operate for the grand opening while the Department of Health reviewed and reconsidered their standards for pools, splash pads, and other water features like the Mini-Mississippi. Ultimately, staff was required to spend an additional $15,500, prior to opening in spring 2026 to address water treatment standards imposed on the feature by the Department of Health as a condition of final approval for the Mini-Mississippi.
Despite these added costs and outstanding change orders that have since been executed, the project has a final surplus balance of $552,148 in unspent funds, which is partially attributed to unspent consultant fees. These unspent funds are tied to a Legacy Grant that expired in June 2026, and will be reallocated towards other Legacy Grant-eligible projects in the Park District.
Final Budget Summary:

Relationship to the System Plan: